Heat Power Engineers Complete Repairs of Energy Unit at Lipetsk HPP-2
The employees of the Lipetsk branch of PJSC “Quadra - Power Generation” have completed repairs at power unit No. 5 at the Lipetsk HPP-2 (heat power plant). The company invested almost RUB 8 m in this project.
“Our specialists have completed a comprehensive set of repairs and restoration works at the turbine and boiler, which will ensure their further efficient and reliable operation,” explained Vitaly Gordeev, Chief Engineer of the branch of PJSC Quadra - Power Generation - Lipetsk Generation.
The energy unit was under repairs for 2 months. During this time, the heat power engineers completed the repairs of the gas-air path with the replacement of insulation, drilled slip rings, cleaned the oil system, and performed other necessary works.