“Quadra – Power Generation” to Assign over RUB 1.1 M for Scheduled Repairs of Boiler at Alexin HPP
The Alexin HPP (heat power plant) of the Central Branch of PJSC “Quadra – Power Generation” has started the scheduled repairs of boiler No. 6. The cost of the work to be completed by the end of July will amount to RUB 1 m 190 thousand.
The specialists will test the metal, repair the draft mechanisms, and restore the thermal insulation and clothing of the boiler. The work will not affect the energy supply of consumers.
“The complex of the works will increase the efficiency of the equipment and increase the reliability of its operation,” noted Sergey Finkelstein, Chief Engineer of the branch.
The Alexin HPP provides heat to 70% of the residential stock of the left-bank part of the city of Alexin, and supplies heat and steam to large enterprises of the special industrial zone created here – the territory of advanced socio-economic development (TASED).